Tahoe Water Line Supply / Paving (Summer 2015)

Bond Project Tahoe

 

Start Date: October 16, 2014

Estimated Completion Date: January 15, 2016

 

Project Info: 

  • Project Manager: Chris Zunino; (916) 264-4075 Ext: 1022
  • Architect: HMR
  • Contractor: Seward Schreder Construction
  • Source Funding: Emergency Repair Program

Construction Description: Replace water line and paving

 

Project Status:

Last Week (7/23/15):

  • Lime treating
  • water line removal

This Week (7/30/15):

  • Concrete gutters
  • water line removal and replacement