Tahoe Paving (Summer 2015)

Bond Project Tahoe

 

Start Date: June 12, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Chris Zunino; (916) 264-4075 Ext: 1022
  • Architect: HMR/PMG
  • Contractor: Seward Schreder
  • Source Funding: Deferred Maintenance Program

Construction Description: Removing existing pavement and repaving on site

 

Project Status:

Last Week (7/7/15): 

  • Lime treat
  • Rough grade

This Week (7/14/15):

  • Grade and compact AB
  • Valley gutter