Phoebe A. Hearst Fire Alarm Upgrade

Bond Project Phoebe Hearst

 

Start Date: June 12, 2015

Estimated Completion Date: August 28, 2015 

 

Project Info: 

  • Project Manager: Anthony Lea; (916) 264-4075 Ext: 3616
  • Architect: HMC
  • Contractor: Studebaker Brown
  • Funding Source: Measure Q

Construction Description: Fire alarm upgrade

Project Status:

Last Week (7/14/15): 

  • Pulling wire

This Week (7/23/15):

  • Trenching to 4th & R to protect kids from equipment
  • 70% complete