New Technology Roofing

Bond Project Sacramento New Technology
In-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionAfterAfterAfterAfterAfterAfterAfterAfter

 

Start Date: May 15, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Jeff Bozeman; (916) 264-4075 Ext: 3617
  • Architect: HMR
  • Contractor: Clark & Sullivan
  • Source Funding: Deferred Maintenance Program

Construction Description: Replacing roofing 

 

Project Status:

Last Week (7/14/15):

  • Demolition 
  • Re-roof
  • Removing roof 3 
  • Cool coating

Last Week (7/23/15):

  • Rolling equipment on roof
  • Tearing off roof #3 
  • Cool coating roofs 2,5,10

This Week (7/30/15):

  • Rolling equipment on roof
  • Cool coating roofs 2,5,10