Kit Carson Kitchen/MP Flooring (Unbundled) (Summer 2015)

Bond Project Kit Carson International Academy

 

Start Date: June 12, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Chris Zunino; (916) 264-4075 Ext: 1022
  • Contractor: Landmark Construction
  • Funding Source: Emergency Repair Program

Construction Description: Kitchen/MP flooring maintenance on site 

Project Status:

Last Week (7/7/15):

  • Abatement 
  • Floor prep

This Week (7/14/15):

  • Epoxy kitchen floors