John F. Kennedy Stage Drapes and Rigging

Bond Project John F. Kennedy

 

Start Date: May 15, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Jeff Bozeman; (916) 264-4075 Ext: 3617
  • Architect: HMR
  • Contractor: Stagecraft Industries, Inc.
  • Funding Source: Deferred Maintenance Program

Construction Description: Replacing stage drapes and rigging in theater

 

Project Status:

This Week: 

  • Fabricating drapes