Hiram Johnson AC Paving Black Top

Bond Project Hiram Johnson
In-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-ConstructionIn-Construction

 

Start Date: May 25, 2015

Estimated Completion Date: September 15, 2015

 

Project Info: 

  • Project Manager: Chris Zunino; (916) 264-4075 Ext: 1022
  • Architect: HMR
  • Contractor: Seward Schreder
  • Funding Source: Emergency Repair Program

Construction Description: New AC Paving for the black top around the site

 

Project Status:

Last Week (7/23/15):

  • Finishing up concrete curbs and gutters
  • Base rock

This Week (7/30/15):

  • Asphalt and Fencing