Caleb Greenwood Restroom (1 Boy’s & 1 Girl’s)

Bond Project Caleb Greenwood IB World School
BeforeBeforeIn-ConstructionIn-ConstructionIn-constructionIn-Construction

 

Start Date: May 15, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Chris Zunino; (916) 264-4075 Ext: 1022
  • Architect: California Design West
  • Contractor: Landmark Construction
  • Funding Source: Deferred Maintenance Program

Construction Description: Modernizing boy’s and girl’s bathrooms on site

 

Project Status:

Last Week (7/14/15):

  • Framing 
  • Top out plumbing

This Week (7/23/15):

  • Plumbing & rough in electrical
  • Framing of boys restroom door