Bret Harte Daylighting In Portable Classrooms

Bond Project Bret Harte

Start Date: June 12, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Jeff Bozeman; (916) 264-4075 Ext: 3617
  • Contractor: Roebbelen
  • Funding Source: Project Green

Construction Description: Installing daylighting in portable classrooms

Project Status:

Last Week (7/23/15):

  • Installing curbs, low voltage in progress

This Week (7/30/15):

  • Installing curbs, low voltage in progress