Bret Harte Children’s Center Fire Alarm Replacement

Bond Project Bret Harte

 

Start Date: May 15, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Anthony Lea; (916) 264-4075 Ext: 3616
  • Architect: HMC
  • Contractor: Studebaker Brown
  • Funding Source: Measure Q

Construction Description: installing new fire alarm system for the Children’s Center 

 

Project Status:

Last Week (7/7/15):

  • Running conduit and wiring

This Week (7/14/15):

  • Wiring and installing devices