Abraham Lincoln Roofing 2015

Bond Project Abraham Lincoln
BeforeBeforeBeforeBeforeBeforeBefore

 

Start Date: June 12, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Chris Zunino; (916) 264-4075 Ext: 1022
  • Architect: California Design West
  • Contractor: Landmark Construction
  • Funding Source: Deferred Maintenance Program

Construction Description: Roof replacement – 42,836 square feet

 

Project Status:

Last Week (7/23/15):

  • Finishing abatement on roof
  • Roof tear off continuing

This Week (7/30/15):

  • Allied finishing up abatement on roof, roofing next week
  • Roof tear off continuing