Start Date: June 12, 2015

Estimated Completion Date: August 28, 2016

 

Project Info: 

  • Project Manager: Chris Zunino; (916) 264-4075 Ext: 1022
  • Architect: California Design West
  • Contractor: Landmark Construction
  • Funding SourceDeferred Maintenance

Construction Description: Modernizing boy’s and girl’s bathrooms on site

 

Project Status:

Last Week (7/13/15): 

  • Hanging drywall

This Week (7/20/15):

  • Electrical Work