Public Construction Project - 03-C1
   

BID No./Title:  Bid No. 03-C1  Rosemont High School Sitework

Project Cost Range:  + 3 Million

See Notice to Contractors

PROJECT SCHEDULE

Mandatory Pre-bid Conference: 7/16/02, 9:00 a.m. - Rosemont High School Construction Site

Due Date: 8/22/02, 2:00 p.m. ***Changed as of 8/13/02***

Bid Award Date:  8/22/02

Preliminary Bid Results: 

BID AWARD INFORMATION

Contractor:  Granite Construction Amount: $2,997,717

Subcontractor's List: 

Triangle Excavation Inc. - Abandon Wells, Demo, Clearing

Centerline - Striping, Seal Coat, Signs, Bumpers

Worldwide Inc. - Construction Staking & Survey

Bid Results: Teichert Construction - $3,434,685

                 Collet Construction - $3,520,750