| Public Construction Project - 02-C12 |
|
BID No./Title: Bid No. 02-C12 Luther Burbank High School Boiler Replacement Project Cost Range: + $100,000PROJECT SCHEDULE Mandatory Pre-bid Conference: 6/13/02, 11:00 a.m. - Luther Burbank HS Due Date: 7/3/02, 3:00 p.m. Bid Opening Date: 7/3/02, 3:00 p.m. Bid Award Date: 7/15/02 Bid Award Information Contractor: MCE Mechanical Inc. Amount: $186,980 Subcontractor’s List:Direct
Digital Controls, Controls/Electrical – LN 702114 Consolidated
Western, Asbestos – LN 277096 Circo
Test & Balance, Test/Balance – LN 624117 Cannon
Water, Chem. Cleaning – LN 01256 Watson
Roofing Inc., Roofing – LN 602298 Official Insulation, Insulation – LN 513034 Bid Results: Airco
Mechanical Inc. - $192,000 Lawson
Mechanical Contractors - $199,200 Luppen
& Hawley, Inc. - $207,500 Walker
Mechanical Inc. - $229,500
|