Public Construction Project - 02-C12
   

BID No./Title:  Bid No. 02-C12  Luther Burbank High School Boiler Replacement

Project Cost Range:  + $100,000

See Notice to Contractors

PROJECT SCHEDULE

Mandatory Pre-bid Conference: 6/13/02, 11:00 a.m. - Luther Burbank HS

Due Date: 7/3/02, 3:00 p.m.

Bid Opening Date:  7/3/02, 3:00 p.m.

Bid Award Date: 7/15/02

Bid Award Information

Contractor: MCE Mechanical Inc.

Amount: $186,980

Subcontractor’s List:

Direct Digital Controls, Controls/Electrical – LN 702114

Consolidated Western, Asbestos – LN 277096

Circo Test & Balance, Test/Balance – LN 624117

Cannon Water, Chem. Cleaning – LN 01256

Watson Roofing Inc., Roofing – LN 602298

Official Insulation, Insulation – LN 513034

 Bid Results:

Airco Mechanical Inc. - $192,000

Lawson Mechanical Contractors - $199,200

Luppen & Hawley, Inc. - $207,500

Walker Mechanical Inc. - $229,500